CompressPdf - Sprint 01

open

about 19 months late (09/12/2024)

99%

8 issues   (0 closed — 8 open)

CompressPdf - Sprint 02

open

about 19 months late (09/19/2024)

76%

5 issues   (0 closed — 5 open)

CompressPdf - Sprint 03

open

about 19 months late (09/26/2024)

100%

7 issues   (0 closed — 7 open)

CompressPdf - Sprint 04

open

about 18 months late (10/03/2024)

93%

12 issues   (0 closed — 12 open)

CompressPdf - Sprint 05

open

about 18 months late (10/15/2024)

97%

12 issues   (0 closed — 12 open)

CompressPdf - UAT-Phase 01

open

about 18 months late (10/24/2024)

17%

15 issues   (0 closed — 15 open)

CompressPdf - Sprint 06

open

about 17 months late (11/18/2024)

18%

33 issues   (0 closed — 33 open)

Invoice Generator - Sprint 03

open

about 17 months late (11/21/2024)

100%

34 issues   (0 closed — 34 open)

Invoice Generator - Sprint 05

open

about 16 months late (12/06/2024)

96%

35 issues   (0 closed — 35 open)

Invoice Generator - Sprint 11

open

about 15 months late (01/17/2025)

73%

19 issues   (0 closed — 19 open)

Invoice Generator - Sprint 12

open

about 15 months late (01/24/2025)

76%

21 issues   (0 closed — 21 open)

CompressPdf - Phase 03

open

about 14 months late (02/28/2025)

66%

29 issues   (0 closed — 29 open)

Algonyx - Sprint 01

open

about 5 months late (10/31/2025)

Planning and initiating the project

92%

42 issues   (0 closed — 42 open)

Algonyx - sprint 04

open

about 4 months late (12/15/2025)

83%

190 issues   (0 closed — 190 open)

Algonyx - sprint 05

open

44 days late (02/24/2026)

21%

60 issues   (0 closed — 60 open)

Algonyx - sprint 06

open

7 days late (04/02/2026)

29%

10 issues   (0 closed — 10 open)

aiaxio - UAT

open

67%

109 issues   (0 closed — 109 open)